Bangladesh: Summit LNG maintenance and gas supply

This dossier follows maintenance at Maheshkhali’s Summit LNG terminal and its announced or observed consequences for Bangladesh’s gas supply.

Last updated : 1 key moments

Where things stand

On 1 November 2026, Petrobangla announces a regasification shutdown from 8 a.m. on 4 November to 4 p.m. on 7 November, local time. Low pressure is possible; the shutdown has not begun.

Bangladesh announces an 80-hour shutdown at Summit LNG terminal

Petrobangla announced on 1 November 2026 a temporary halt to regasification at the Summit LNG terminal in Maheshkhali for emergency maintenance. It is scheduled from 8 a.m. on 4 November to 4 p.m. on 7 November, local time, an interval of 80 hours.

LNG carrier photographed in July 2014. Archive illustration; does not show Summit LNG terminal. Jnzl’s Photos, CC BY 2.0.
LNG carrier photographed in July 2014. Archive illustration; does not show Summit LNG terminal. Jnzl’s Photos, CC BY 2.0. — Jnzl's Photos — CC BY 2.0 https://creativecommons.org/licenses/by/2.0/ — 20 juillet 2014, sans modification.

According to the notice carried by Bangladeshi media, daily LNG-terminal supply to the grid is expected to fall by 320 million cubic feet, from 920 million to 600 million. These volumes describe that supply component, not all gas produced or consumed nationally.

Petrobangla warns that consumers in different areas may experience lower pressure and expresses regret over the expected inconvenience. The maintenance is scheduled, not already completed. The selected sources do not detail the fault requiring intervention or specify pressure reductions by neighbourhood or factory.