Skip to content
What happened next?Continue in this file · Morocco: early November 2026 thunderstorms
File · Morocco: early November 2026 thunderstorms

Casablanca: ONEE reports full restoration of affected electricity substations

Published

ONEE says all substations affected by the 11 November 2026 outage in Casablanca and Nouaceur had their power restored at 8:54 p.m.

The utility attributes the incident to thunderstorms and strong winds, which it says simultaneously damaged four 225 kV lines supplying the Ouled Haddou and Dar Bouazza substations. Its statement, reported on 12 November, says partial restoration began at 6:23 p.m.

The announcement follows earlier reports of a gradual recovery. It concerns electricity supply to the substations and does not establish the full extent of damage caused by the storm.

Sources 2
What happened before?Continue in this file · Morocco: early November 2026 thunderstorms