The agreement covers units 2, 3 and 4, each rated at 213 MW. The reported timetable envisages unit 3 returning eighteen months after work starts, unit 4 after twenty-four months and unit 2 after thirty months.
This is capacity to be restored: the 639 MW is not additional generation already available. The information retained does not establish an actual start date for the works.