A first facility, capped at SAR 1.1 billion, is intended to finance GPU procurement and deployment representing roughly 25 megawatts of IT load. A second, up to SAR 1.4 billion, covers substations, transmission and grid connections.
The power infrastructure is designed to support future data centers with up to one gigawatt of IT capacity. This potential is not already installed capacity. The sources do not specify amounts already disbursed or the commissioning schedule.